Decking Example Quotes

Decking01_edited.jpg

Wood Decking

This is going to be a very "typical" 4m x 4m wood decking installation. First I want to take you through the process we use to install your new Deck. We first insert 100mm x 100mm posts into the ground and these are cemented in to give a real strong anchoring for the timber frame to be fixed to, once the posts are in and have had time to set we will then install the outer timber frame, from this we will install a single or double layer of weed suppression membrane (dependant on the ground that we are constructing the deck on) once the outer frame has been built an d the weed membrane down, we will install the inner frame "noggining" out, so that the spaces left are no more than 600mm x 600mm (approx). We are now ready to install the decking boards, these will be installed with 8/10mm gaps and laid in a horizontal orientation to the way that you enter the Deck to minimise (but not remove) slip hazards, Your Deck is now complete.

​

The quote is again broken down into 2 main areas

  • How many labour days we need to complete the work

  • The materials needed to complete the work

So for this example we will require the following - 

​

  • 10 Labour days

  • 16  100mm x 100mm x 1.2m Posts

  • 19 100mm x 47mm x 4.2m Joists

  • 32 Bags of Postfix

  • 16m2 of Weed Membrane

  • 32 32mm Thick 120mm Wide 4.2m Long Decking Boards

  • Assorted Screws

This would all add up to £4020

Prices are relevant as of the 22nd November 2023

111297762_2971535679610652_6454114564814698957_n.jpg

Composite Decking

This is going to be a very "typical" 4m x 4m wood decking installation. First I want to take you through the process we use to install your new Deck. We first insert 100mm x 100mm posts into the ground and these are cemented in to give a real strong anchoring for the timber frame to be fixed to, once the posts are in and have had time to set we will then install the outer timber frame, from this we will install a single or double layer of weed suppression membrane (dependant on the ground that we are constructing the deck on) once the outer frame has been built and the weed membrane down, we will install the inner frame "noggining" out, so that the spaces left are no more than 600mm x 600mm (approx). We are now ready to install the decking boards, these will be installed with 8/10mm gaps and laid in a horizontal orientation to the way that you enter the Deck to minimise (but not remove) slip hazards, Your Deck is now complete.

​

The quote is again broken down into 2 main areas

  • How many labour days we need to complete the work

  • The materials needed to complete the work

So for this example we will require the following - 

​

  • 10 Labour days

  • 16  100mm x 100mm x 1.2m Posts

  • 19 100mm x 47mm x 4.2m Joists

  • 32 Bags of Postfix

  • 16m2 of Weed Membrane

  • 34 (choice of colour) Composite Decking Board 4m

  • 8 Composite Decking Fascia Board

  • 8 Composite Decking Trim

  • Assorted Screws

This would all add up to £4750

Prices are relevant as of the 22nd November 2023

Decking Example Quotes: Rates

Follow

  • Facebook
  • Instagram

Contact

07515144352

Address

1 Longfield Avenue Halifax United Kingdom HX3 7BS

©2016 by TLC Joinery & Landscaping. Proudly created with Wix.com

bottom of page